CA97- Selected routing ?

Former Member
0 Kudos


Hello dear all,

I have one material with 3 production versions.

When I launch CA97 transaction the task list of the first production version is not selected.

The routing with the first number is used for the calculation.

Do you know what is the rule?

May I change this behavior?

Thanks a lot.

Best regards,

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

A routing selection via production version is not available on CA97.

You can either enter the desired routing data (PLNNR, PLNAL etc.) or the routing is selected automatically via the selection ID. The selection ID is defined on the customizing transaction OPU5 for order type 'LA'.

BR

Caetano

Former Member
0 Kudos

Hello Caetano,

Thanks for your explanation.

I understand the standard behavior is, on one hand for planned order the routing is selected with the production version, on the other hand in house production time could be calculated with an other routing in CA97 calculation.

Best regards.

Jb

jmc_star_agc
Explorer
0 Kudos

Despite the fact that we specify the exact routing we need in CA97N, PLNTY + PLNNR + PLNAL + MATNR + WERKS, system still controls the selection ID and refuses our input if it does not respect the content of the selection ID.

So it is not an "OR" but well an "AND" logic.

Br,

JMC