on 07-29-2014 7:05 AM
Dear All,
WE are trying to do progress analysis to calculate BCWP and BCWS for this we are using budget as a base. we are not getting any BCWP and BCWS values where as all other values like POC agg. Non Agg. are coming properly. Kindly suggest.
We have maintained following things.
For Activity we are maintaining Plan method as Time proportion and actual as Work.
For WBs we are maintaining Plan method as well as actual as 0-100 method
and after that we are confirming activity and executing CNE1 and after that CNE5.
Regards
Dheerendra Patil
Dear Dheerendra / Shivali,
please check the following things
Regards
PP
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit,
According to your reply I have checked the report"CHECKREPORT_PROGRESSANALYSIS" and there it doesnot show any error.Also I have used budget overall as my base for earned value analysis.I have already gone through the links suggested by you and I fail to get the desired solution.
Regards,
Dheerendra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.