on 07-28-2014 1:41 PM
Hi,
Is there any sequence for scheduling dba jobs in DB13(Check DB, Verify DB,Update statistics etc)?.
Regards
Chandrasehkar
Hi Chardrashekar,
There is no sequence as experts told, please have a look at below notes/Link
1) 25152 - New scheduling calendar in CCMS (DB13) ORACLE
2) 66322 - CCMS: Database administration (transaction DB13)
3) http://help.sap.com/saphelp_nw70/helpdata/EN/02/fb1c42128a5733e10000000a155106/content.htm
Thanks
Pradeep
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You 1st check DB.
You then update stats
And then verify DB
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Chandrasekhar,
There is no sequence for this . It is based on requirement and suggestions from EWA report.
Ideally we have Update statistics & Check DB configured on daily basis.
Verify DB to be scheduled either on weekends or low load activities as it consumes good amount of DB resources. So plan this job accordingly.
Regards,
Deepak Kori
You normally schedule on a daily basis:
UpdateStats first and 1h later CheckDB
Reason for this is that otherwise you may get warnings related to index stats being obsolete
Then on weekend run once VerifyDB and Cleanuplogs
Note VerifyDB takes a long time.
This is a best practice, I have not seen this documented on any note.