Hello experts

I am trying to check available capacities in planning book & found some ambiguities.

In /SAPAPO/RES01, factory calendar maintained in the resource is say Z1, but in the same page, the capacity profile tab uses a different calendar.Say in Z1, if X/X/XXXX is a working day, the one present inside capacity profile considers it as a holiday & the  available capacity doesn't reflect in planning book.

In ECC, the plant where this work center is defined follows calendar Z1.

So my doubt is which calendar the capacity profile follows & how to ensure that it follows the same factory calendar Z1?

Regards

Soum

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hello Soumyajit,

few things you can check,

Plant and work center calender assignment should be same, Plant has precedent over WC

Check if in CFC9 you have correct change transfer mode set for resource.

Once calender updated in ECC, use program RSIMPCUST to rebuild the tables for factory calendars in APO and then run /SAPAPO/CRES_CREATE_LC_RES to extend the resource in LC

also run /SAPAPO/TIMESTREAM_UPDATE for any time stream update.

This will update capacity profile as well resource capacity in planning book/ planning board.

Hope this info will help you,

Thanks,

Rajiv