Hi SAP Expert and Guru,
Currently I am gathering the Invoice Document Number from Project ID and below is my table flow.
Project ID/ WBS is being inserted to table PRPS-PSPHI,
Then the Object Number from PRPS-OBJNR is being captured and being used in table COEP-OBJNR to derive the value in COEP-BELNR.
Later the value in COEP-BELNR is being used in table COBK-BELNR to derive the invoice number in COBK-REFBN.
My question now is, is there any other table that we can use to replace table COEP, in order to get the Object Number OBJNR linked up with the Document Number BELNR which can be used in table COBK to derive the Invoice Number.
Kindly Advise and consult.
Thank you
Regards
Leonard Tan
Why dont you try to use the OBJNR from PRPS and use it in the COFP table?
I think you should be able to get the details you are looking for.
Let us know if it helps.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.