on 07-22-2014 10:41 AM
Hello,
The PO's currency comes from the supplier one.
But i want to change as the currency of the SC for some plants.
Is there any possibility to do that by customizing or i have to code it?
thnaks,
Meriem.
If you are not using vendor sub-range, then you can't able to use more than one currency for one vendor.
Currency comes from vendor master record to PO and it is locked. You can't change it at PO level.
If you want to use more than one currency for one vendor as per plant, then you can use vendor sub-range.
Have a look into the document http://www.sdn.sap.com/irj/scn/go/portal/prtroot/docs/library/uuid/d0fe1f3c-aaab-2e10-baa8-b684e5f92...