SRM PO Document date is getting replicated to ECC as Delivery date

Former Member
0 Kudos

Hello SRM experts,

Please guide me on the following issue. We are using extended classic scenario. SRM 7.0

Delivery date is not getting reflected in the ECC delivery date field.

To know whether this is an standard issue ?

Is there any way out to make proper replication to ECC ?

What might be the reason for this ?

SRM PO created with Delivery date "08/07/2014".

But current date(Document date) "01/07/2014" is picked in delivery date

Delivery date is getting reflected in the Statistical delivery date field under Item details --> Delivery schedule tab

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

When you create a PO , delivery date is calculated by adding planned delivery time from Purchase info record.

The delivery date calculated thus, is defaulted into the PO for del date and st del date.

If you change the delivery date thus defaulted, without making a manual entry in st del date, the date you entered will default to st del date too,

This change will not happen, if you make a manual entry in the st del date field before you change the del date in the po or you output the PO and then change the del date in the PO.

In case you want to change the delivery date in ECC this exit can help :EXIT_SAPMM06E_012

Thanks

Ankit