Shifting of Schedule Lines

Former Member
0 Kudos

Here goes the scenario:

1. In the production environment, a Standard Order is created with Requested Delivery Date as 15th July 2014.

2. After all the data is entered, the system automatically shifts the Schedule Line Date to 21st July 2014.

3. If I create the same order in Quality/Testing Environment(Replica of Production Server), the schedule line confirm to 15th July 2014 only.

4. Enough Stock of material is available in both the environments and Material Master is exactly the same in both the environments.

Please let me know all the possible reasons that might be causing the shifting of Schedule lines in the Production Server.

Accepted Solutions (0)

Answers (4)

Answers (4)

0 Kudos

Is route is same in both orders?. and r u using ATP r GATP?.

former_member223981
Active Contributor
0 Kudos

Are you absolutely certain there is sufficient quantity available on July 15th? Check CO09 and post a screenshot here.

Other things to check that have not been mentioned above:

- Are the routes the same in both examples? Check transaction 0VTC for the transity time of the route.

- Are the pick / pack & loading times the same? Check transaction OVLZ to ensure they are the same as yuor other example.

- Are you using Route Schedules in the example?

phanikumar_v3
Active Contributor
0 Kudos

What was the Checking rule taken in sales order--any differences between QA vs PRD???

Check in environment→availability.

it will gives an idea--why system going for Forward scheduling here.

Any differences you found in OVLY??

what was the date you find at header as requested delivery date??

Pl update

Phanikumar

Lakshmipathi
Active Contributor
0 Kudos

One simple option is compare the Shipping dates from schedule line where at the bottom screen, you find this tab.  As per your indication, all dates should be identical to Quality client.

G. Lakshmipathi