on 03-28-2007 3:49 AM
Integration model for Sales Orders to APO is failing and in the CIF the error says "Customer requirement G BR 0082372353 900010 0000: liveCache problem, retu".
This error appears everytime you we run the integration model and it says in the Job log; ABAP/4 Processor: SYSTEM_CANCELED.
Note that this is "not" manually stopped but it still gives this error.
Hi Kailash,
Run /SAPAPO/SDRQCR21 in apo for the part contained in your delivery document, which is failing. While running the report, check the radiobutton, Build the requirements from Doc.Flow table. This will remove the inconsistencies remaining in the requirement table on R/3 side.
Try this and let us know, if you could succeed.
Regards
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hai Kailash,
Just few preliminary steps. You may have done these but check it.
1. Is all tha master data related to the sales order CIFed to APO before this?
2. Are there any CIF quue blocks? check SMQ1 and CFQ1.
3. Check for any locks on the customer requirements in ECC.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
try this
run a liveCacheconsistency check on OM17 in APO
if this doesnt help
do a Compare and Refresh with CCR to sync
also check the queues on outbound for any blocks on related objects
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.