PS Revenue Planning ( Tracking History )

Former Member
0 Kudos

Hi All,

Kindly advice how can we track the history changes in revenue planning, whether it comes from SD Doc, WBS billing plan or CJ43.

I tried couple things but it seems that there is no tcode to track the history changes.

I can track the changes in Planning cost through CJI4.

Appreciate for the advice.

Thank you.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Nies,

Have you tried using cn54n and cn55n for checking the planned revenue and for the reference of sales order documents that have been assigned to the project?

Regards

Varun

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Nies,

Try activating a user status with "Write Plan line items" option activated. Please check the cji4 report once done. Kindly mark this as helpful if it helps solve your query. Use cji9 report in case your performing hierarchical revenue planning.

Regards

Varun

Former Member
0 Kudos

Hi Varun,

We already activated ' Write plan line items ' in our user status. I think the Business transaction only can capture for Planning cost not for Planning revenue.

Appreciate for your response.

Thank you.

Nies