Extractor - finished with RC:8 - Incorrect Client. Called 001

Former Member
0 Kudos

Hello experts,

In our Solution manager in SLG1 we are having the following error:

=> Finished with RC: 8  ( INCORRECT CLIENT. CALLED: 001 REACHED: 100 )

Message no. BL001

Normally 100 is the client we use for the configuration of Solution Manager. Could you please help how to solve this?

In which step of Solman Configuration should we check and correct this issue?

Thanks and Regards

Accepted Solutions (1)

Accepted Solutions (1)

nirmal_konchada
Active Contributor
0 Kudos


Hi,

Can you please check the 001 client RFCs in the managed system setup step 3 for SSM.

It seems that the RFC assigned for 001 have 100 as the client.

Regards,

Nirmal.K

Former Member
0 Kudos

Thanks for the answer nirmal.

Now that I check step 3 (Solman as a managed system itself) I see that the info on that step is emtied and nothing can be done.

I check and see that this is the same with all the other solutions too.

These steps were successfully finished before.

divyanshu_srivastava3
Active Contributor
0 Kudos

Hi,

Can you check this in BASIC config.

Use report : RS_MANDT_UNIQUE_SET function module

Now solman setup say

"If you have copied your SAP Solution Manager from the default client 001 to another client (such as client 100), and you want to use the local BW configuration in the copied client, execute the RS_MANDT_UNIQUE_SET function module for the new client"

Also check with RSA1.

Regards,

Divyanshu