on 07-12-2014 1:37 AM
Hi PS experts
I am facing issue with regards to the report "S_ALR_87013532"
I created projected structure and assigned only one materiel component of total value 15,000 EUR at activity level. Apart from that I have not done cost planning for any other objects in the project.
However when i checked the report "S_ALR_87013532" planned cost is showing as 15,000 at material component level but its showing incorrect figures (21,263) at activity level and its parent level ( Network and WBS element level).
Below are the screen shots of Project structure & the report, please have a look at it & share your expert opinions on the possible reasons for this kind of behavior.
Thanks and Regards,
Naveed
Hi Wasim,
Please Check whether u have maintained any Activity type and Work in Internal Activity. if that is so remove the activity type and check the report.
Regards
Avinash
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Please check the report again after executing CJEN.
Also check the settings of your Costing variant-> valuation variant in OPL1. (May be you have maintained planned price of material in MM master and check its relevancy with valuation variant strategy)
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.