Planned cost showing incorrectly in the reports

Former Member
0 Kudos

Hi PS experts

I am facing issue with regards to the report "S_ALR_87013532"

I created projected structure and assigned only one materiel component of total value 15,000 EUR at activity level. Apart from that I have not done cost planning for any other objects in the project.

However when i checked the report "S_ALR_87013532" planned cost is showing as 15,000 at material component level but its showing incorrect figures (21,263) at activity level and its parent level ( Network and WBS element level).

Below are the screen shots of Project structure & the report, please have a look at it & share your expert opinions on the possible reasons for this kind of behavior.

Thanks and Regards,

Naveed

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member341917
Active Participant
0 Kudos

Hi Wasim,

Please Check whether u have maintained any Activity type and Work in Internal Activity. if that is so remove the activity type and check the report.

Regards

Avinash

former_member195427
Active Contributor
0 Kudos

Hi

Please check the report again after executing CJEN.

Also check the settings of your Costing variant-> valuation variant in OPL1. (May be you have maintained planned price of material in MM master and check its relevancy with valuation variant strategy)

Thanks