STOs and Productions order are not lined up. Dates are off

Former Member
0 Kudos

Hi Experts

I have a production order and STO with different dates. I would expect no gap between Prod order and the STO. I have checked Planned delivery time,GR/GI at both supplying and receiving plant . Everything looks fine. Please Advice

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Ganpath,

In general, both of those objects are executables.  In most applications, the relationship between the dates of STOs and the dates of Production Orders is not directly determined by the software,  It is only through careful design and execution of the overall process that you achieve dates that line up; assuming, of course, that is your business requirement (not everyone wants dates to line up).

So, it depends upon how these two objects were created.  Can you please describe how they were created?