Hi,

I am having a scenario where I want to create a delivery for a material having the schedule line as CN.

I do not want the SO requirement to get captured to MRP.

The stock will be  produced elsewhere and brought in to the SO.

The "Item rel.f.del" has been ticked in the schedule line category definition.

But still this is not getting picked to the delivery document.

Appreciate any thoughts on this.

Thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

srinu_s1
Active Contributor
0 Kudos

Check the sales order schduline lines, the confirmed qty ? if is zero, you can't do the delivery.

And also please paster the CN screen shot?( May be check if some one marked the fields Req/Assembly and availability is marked)