Hello Experts,
I need to have a workaround of transaction CO02. Actually, we have already implemented PS by using Project Stock but the problem is that we have almost thousands of production orders that will come into unrestricted stock after production. For these orders we want to make an account assignment for a project and we want that MRP to see all these production orders as entering project stock after production. If I do the same by CO02, it is very difficult for me to do it individually for each production order. So, is there any way to configure our need for passing from using unrestricted project stock to project stock ?
Thanks,
Kumar Srinivasan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Then try implementing the following logic. Not sure if this can help you.
Use a material that is set up to trigger the production order and attach this material to a network activity that is set to be reserved for project stock Q and can only be GI to that WBS element. The planned costs are recognized in the project but the Actuals are only recognized when the finished material is GI back to the project. You can use your planned production orders and MRP in exactly the same way but they are just linked back to the project when they are completed.
If you need to transfer planned orders that are already in place then it can be done in MM. There’s a goods movement type specific to where you need to reference the WBS element that is set for requirements grouping.
Regards,
Amit
Hi Srinivasan,
why not you use CO10 transaction?
if you want to after production stock should come in project stock. then go through CO10 transaction will fulfill your requirement.
after confirmation of production order check MMBE transaction whether is your material stock so it will show project stock and storage location.
just i let you know CO01/2/3 transaction code also for production order creation edit and display but it's for PP side so you can not link with project so i suggest you to go though CO10 transaction only.
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Then you can go though MD51 transaction where we can execute MRP based on project or wbs.
here we have to check mark hierarchy so what was the material in component overview MRP will run on those and system will create PR for RM
& Plan order for SFG/FG so plan order will convert into production order
Then confirm production order
Check stock in MMBE
in another way PR for RM will be convert into PO then MIGO and check in MMBE stock is there or not?
so when you are going to confirmation production order it will ask for RM once back flush is on then RM will consume in production order.
Regards,
Sanjeev
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.