on 07-09-2014 7:46 PM
Anyone have any experience/success implementing GTS with a subcontracting process that involves crossing borders?
I have been refering to SAP note 139724 - INTRASTAT: Subcontracting for reference becuase our process flow is very similar. Only difference is Intrastat is not involved.
Thank you, Jeff
Hi Jeff,
Yes, I've implemented subcontracting with GTS a couple of times without problems. The outbound proforma creates an Export Declaration for OPR, and an Import Declaration can be created from the inbound Goods Receipt to clear down the stock. What more could you need to know?
Regards,
Dave