Operation 003000000003, activity P: Minimum interval > Maximum interval

Former Member
0 Kudos

Dear Seniors,

I encounter this error when I try to CIF the PDS in APO and I cannot pass it. I've tried to look up in different forums and the solutions that work there, don't work in my situation.

I've checked my routing and I don't have defined any Wait time, Std. queue time or Std. move time.

If you have any idea regarding the cause of this error , please share.

Thank you,

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I got the solution for this:

First of all, in SAP APO, in trx. /sapapo/cc, the detail information for the error can be seen.

In my case the error was in a sub assembly. I has a minimum wait time of 30 minutes, for operation 0030, and no maximum wait time defined.

You can delete the minimum wait time, or set a greater maximum wait time for the operation.

I hope this will help somebody that has the same error.

Answers (0)