Can we link Activity Elements in SAP PS ?

Former Member
0 Kudos

Hello Gurus,

We have some requirement, whereby, we will have to place order at activity element level and also schedule them - that is there should be linking between activity elements coming under same activity.

Kindly let me know how to do it...

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi KS,

Please note that we cannot allocate materials, or assign milestones, documents or production resources/tools to activity elements. Activity elements do not have relationships.


As told earlier, the dates for the activity elements are calculated with respect to the start date or the finish date of the corresponding activity. Enter an offset to the start or finish of the activity to specify the start/finish of the activity element.


Regards

Varun


Answers (4)

Answers (4)

former_member195427
Active Contributor
0 Kudos

Hi,

Its SAP std. that you can not perform relationships among activity elements.

So, its not possible.

Thnks

Former Member
0 Kudos

Hi

Activity elements doesn't contain relationship , so not relevant for scheduling. more over you cannot assign PS text, milestones, material components and documents.

so  activity element does meet the above requirements

vijay

Former Member
0 Kudos

I dont think you can do that.

Former Member
0 Kudos

Hi KS,

We can make use of offset to start and offset to finish for scheduling of activity elements linked to a particular activity. The duration of the internal activity needs to be provided before providing the values for offset to start/offset to finish. 

Regards

Varun