on 07-09-2014 12:15 PM
Hello Gurus,
We have some requirement, whereby, we will have to place order at activity element level and also schedule them - that is there should be linking between activity elements coming under same activity.
Kindly let me know how to do it...
Hi KS,
Please note that we cannot allocate materials, or assign milestones, documents or production resources/tools to activity elements. Activity elements do not have relationships.
As told earlier, the dates for the activity elements are calculated with respect to the start date or the finish date of the corresponding activity. Enter an offset to the start or finish of the activity to specify the start/finish of the activity element.
Regards
Varun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Its SAP std. that you can not perform relationships among activity elements.
So, its not possible.
Thnks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Activity elements doesn't contain relationship , so not relevant for scheduling. more over you cannot assign PS text, milestones, material components and documents.
so activity element does meet the above requirements
vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I dont think you can do that.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.