Activity milestone function workflow set up

Former Member
0 Kudos

Hi Experts

Please let me know how to set up workflow for activity milestone.

I would like to trigger a mail before certain days ahead of planned completion date.

Please share if any document detailing this requirement.

thanks and regards

ramSiva 

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member195427
Active Contributor
0 Kudos

Hi ,

Please go through followin sap help document:

Define Workflow for network milestones - Project System - SAP Library

Thanks

sanjeevc
Active Contributor
0 Kudos

Hi,

Go through below direction.

1. Assign a milestone to any activity/& WBSE according to your requirement.

2. Then go to functions tab in Milestone. Select "start workflow task"

3. Set the milestone date, when you reach/ achieve this milestone, trigger the  workflow.

4. Finally in "Change" field put "+" (Status set). Define whether you want to trigger it only once, in "Once" field. Then finally in "Activa" (Activate function) field, chose how want to activate it

Check with abaper

Regards,
Sanjeev

Former Member
0 Kudos

Hi,

I am not sure but I think you can create a new user status. Set this status on 5 days or as your desire before planned completion date and based on this status, a workflow mail will trigger. Discuss it with your WF consultant.

Also go thru the below link:

http://scn.sap.com/thread/1492335

http://help.sap.com/saphelp_470/helpdata/en/4c/227de546e611d189470000e829fbbd/content.htm

Regards

Shishir