<b>Hi All,

Can any1 pls let me know where is the relationship maintained between System status, User stauts & Processing Status of a Project in cProjects? Ex: Project status in cProjects will be, say Created (I1700). But in the table level, it stores as "00" or "10" if its Released. Where is the relation between these maintained?

Your views would be highly appreciated..

Warm Regards,

Sujay G!</b>

Accepted Solutions (1)

Accepted Solutions (1)

former_member189058
Active Contributor
0 Kudos

Hi Sujay

The processing status of a project/phase/task is maintained in the DPR_project/phase/task table. in the field PROC_STATUS_OWN.

Its data element is: DPR_TV_PROC_STATUS_OWN and domain: DPR_PROC_STATUS. The value range of the domain specifies which value means what. eg. 00 -> CREATED

Regards,

Reema.

Pl award appropriate points to all useful answers.

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Sujay,

Please see my anser in other thread as well.

Purpose of this addition parameters (00, 10 etc.), as I know, are the following:

1. For the workflow.

2 For the evaluation.

Kind regards,