03-27-2007 11:33 AM
hi,
i schedule a job for every 5 min using SM36 and SM37
how i can remove background job schedule.
03-27-2007 11:36 AM
Hi!
In SM37. Select only "enabled" jobs. You'll see your job.
Then choose Job - Modify menu.
Stop scheduling.
Regards
Tamá
03-27-2007 11:45 AM
HI,
Select the Job using SM37 transaction. In the Menu Choocse
Job ---> Cancel Active Job.
Before you do this it may be good idea to check the pid using SM50.
It will be using a Background work process. Check the pid and the status.
Select the same and in the Menu Choose Process --> Cancel with Core.
You can refresh and check in SM37 for the Active and Cancelled Jobs.
Regards
Sudheer
03-27-2007 11:45 AM
hi
just select the bg job from SM37 rignt click stop the job or kill the job it will ges stop.
M Kalpana