Project Planning Board - Progress % at WBS level in CJ2C

0 Kudos

Dear Colleagues,

We are using PPB to follow project progress using transaction codes CJ2C or CJ20N with PPB view.

When we have a network activity confirmation we can see the acitvity progress percentage at the field  RCJ_PS_PLAN-ABARBA (Processing % of work).

But the accumulated percentage is not displayed at WBS level. I mean, at WBS level this field is left blank using CJ2C or CJ20N.

Using CNE5 report, we areable to see the percentage in all levels.

Does anyone knows any configuration to have the same CNE5 view in CJ2C?

Thanks,

James R. M. Francisco

SAP PS/IM Consultant

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Francisco,

Have you tried using the structure overview report (cn41n)? Is the field blank (Processing %) at WBS level in cn41n report as well after confirming the activities beneath it?

Can you please attach the screenshots of views you are watching in cne5 and cj2c?

Regards

Varun

0 Kudos

Hi Varun,

Thanks for the fast repply!

Please see below the CJ2C and CNE5 screen shots:

Thanks and Regards

James