on 07-01-2014 1:35 PM
Hi Experts,
I have created a production order of a material and its Inspection lot is automatically created but the inspection lot created does'not have sample size from the stock as a result I am unable to perform result recording of a inspection lot.
Please correct me if i am wrong.
Thanks
Saurabh
Hi,
Can you post a snapshot of the error message?
inspection lot created does'not have sample size from the stock as a result I am unable to perform result recording of a inspection lot.
You can have MICs (without sampling procedure) in the inspection plan and do the result recording. Only impact it will make is that sample size would be ZERO but it won't stop you from entering the results.
Since you are not able to do result recording, I assume there is something else or may be MICs are not assigned to inspection plan.
Pl post the error details.
ntn
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Saurabh,
Based on ur Q?,it may be due to of inspection type IMG setting.
Plz check the Physical sample type option in below path
SPRO--> QM-->Quality inspection-->inspection lot creation-->Maintain inspection type-->select inspection type -->select the required option based on inspection type in Physical sample type option.
And reset the sample in QAC3 and assign again QA02 and recheck the process.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Saurabh Mishra.
Kumar & Barjatya's said is right. and more you can consider for solve this problem as below step;
- You must change the sampling procedure in the inspection plan. After you have reset the sample
in QAC3
1. First you must change the sampling procedure to fixed sample (assuming you have 100%
inspection at present) in QDV2 or
create a new sampling procedure (as Naik remarked) with fixed sample in QDV1
2. Then assign the changed sampling procedure in the inspection plan through QP02
3. Then assign a sample quantity in the inspection plan in the same transaction (QP02) for the
inspection characteristic to be inspected
4. Save the inspection plan, and run QA02 where you re-assign the updated inspection plan and
re-do sample calculation.
For GR based lot i have already stated what has to be done. In case of an inspection lot caused
due to the GR from a process or purchase order, cancel the GR. The inspection lot is also
cancelled. Then follow steps 1 to 3. In the 4th step after saving the inspection plan, simply do the
GR again, It should work out.
Regards,
Jeong, Yeong-Chul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Saurabh,
If you have assigned the correct sampling procedure, then check what is the sample size that should have been calculated and what is the inspection lot quantity.
Regards,
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Saurabh,
Did you assign the sampling procedure to MIC in the inspection plan?
Br
KK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.