Accounting Integration Error

I have setup Accounting Integration for Internal Order Automatic on saving.

However when I run calculate Button it says There is no internal order for project


I didnt find anything in cockpit COCPCPR

PPM and ERP are on same server.

I have maintained controlling scenario CPR1

Assigned it to Project Type *

Please help.

Thanks and regards,

Niketan

Former Member
replied

Hello Niketan,

This is a customizing error

No account assignment exists for the project definition - no costing.

Integration with other mySAP.com components

Collaboration Projects

   Controlling

     Settings for Easy Cost Planning:

        Here you need to choose a costing variant that is defined for

        Ad Hoc costing in customizing under:

     Controlling

  Product Cost Controlling

   Product Cost Planning

    Ad Hoc Cost Estimate

       Define Costing Variants

the configuration guide is in note 1119326.