Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Business Activity for MDG-F


Hi

Is theren any BC set activation required for MDG-F business activity for MDG 6.1?

There is only one Business Activity (CMP1) in configuration now.

For another activites like ACC1-6 and so on is there SAP delivered BC set or need to  create it manually against each Change Request Type and logical actions?

Former Member
replied

Hi Sanjay,

if you want to use business activities in MDG 6.1, yes, you have to create them manually. The question is: why do you need business activities for MDG-F in 6.1?

The standard delivery does not require business activities.

Best regards

Michael

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question