Reg: Mutliple specifications

former_member184571
Participant
0 Kudos

Hi experts ,

can you please explain me the steps , how to add dependent characteristics specs in inspection plan...?

i am unable to create . When i am tryng to add material and customer in EWB  against inspection characteristic, i am getting the message

"No valid material routing allocation exists for material (XXXX) Customer ( XXXXX).

Message no. CZCL014

Regards,

daya..

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member207800
Active Contributor
0 Kudos

You have to register the material-customer assignment at task list header level before you define dependent characteristic specification.

And "the dependent characteristic spec." and "the multiple spec." are different functionallities.

Regards

former_member211618
Contributor
0 Kudos
former_member184571
Participant
0 Kudos

Hi ,

Thanks for sharing the info.

still i am facing the issue " Material assignment is not available : while adding dependent characteristics in EWB.

Regards,

Daya