on 06-27-2014 7:06 AM
Dear friends, Good Morning!
why am I getting two different results in MD04 for the same material but the MRP AREAS are different.
one MRP AREA is for a specific storage location (please find the screen shot below)
Second MRP AREA is same as the plant (Please find the screen shot below)
What could be the reason? kindly guide me.
Best Regards...
Andy
Dear all,
Any idea why the results are showing different for the same material and different MRP Areas
Best Regards....
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check whether the material is assigned to those 'TWO' storage locations or not.
Anandkumar KS
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.