06-27-2014 9:05 AM
Hello,
I have chosen budget update profile 00300.
I have activated in the system to carry forward the budget associated to the documents.
From my understanding when you do the carry forward of an earmarked fund or a PO just the Commitment Budget associated to that element is carried forward. Is there any chance to copy that budget automatically also to the Payment Budget?
Please let me know.
Regards,
Daniel
06-27-2014 9:53 AM
Hi,
Yes, you can do it with generation of automatic budget lines, following customization in IMG - Public Sector Management - Funds Management Government - Budget Control System (BCS) - Budgeting - Budget Entry - Budget Entry Documents - Additional Budget Line Items
Regards,
Eli
06-27-2014 9:53 AM
Hi,
Yes, you can do it with generation of automatic budget lines, following customization in IMG - Public Sector Management - Funds Management Government - Budget Control System (BCS) - Budgeting - Budget Entry - Budget Entry Documents - Additional Budget Line Items
Regards,
Eli
06-27-2014 11:31 AM
Ok. Thanks
Should I activate the aditinal budget line for CCF and create a derivation strategy? but what kind od derivation strategy?
Thanks in advance
06-27-2014 11:36 AM
A strategy which would create a payment budget line, in case of a commitment budge created during carry-forward process (based on budget type, if you have a special one for CF or budgeting process as source field, for example).
06-30-2014 1:54 PM
Hello,
I sounds perfect what you say, but I am not sure how to carry it out. Should I create a Derivation rule?
I have selected as Source field the field "Original Aplication" (Value = "CCF") and as target field the "Activation of aditional lines" (Value = "X").
Actually I do not know how to make the system understand what you are explaining me.
Please let me know.
Regards,
Daniel
06-30-2014 2:07 PM
... and budget category '9F' as target field. Also, don't forget to switch the flag for 'CCF' in 'Activate Additional Budget Line Items' activity.
06-30-2014 2:10 PM
Hello again,
OK. Source field "Budget Commitment" and target "Payment Commitment".
Condition = Budget Process for Carry Forward.
It is not working yet. Shoudl I activate anything more? I have activated additional budget line for any Carry foreard process.
Please let me know.
Regards,
Daniel
06-30-2014 2:22 PM
06-30-2014 2:29 PM
06-30-2014 3:32 PM