cancel
Showing results for 
Search instead for 
Did you mean: 

Network Activity to WBS element settlement status

Former Member
0 Kudos

Hi all,

Our Customer requires a custom report which will reflect whether settlement has been run from network activity to WBS element.

Is there any table which shows whether settlement for a particular network activity has been performed.

Any other suggestion is welcome except CJI3 report..

Thanks in advance

Regards,

Pabak rout

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi,

If your requirement is to exptract a report of WBS/NWA on which settlelemt have been performed, then use CN41.

Select option of 'status' from choose field icon. In report which Project Object have 'SETC' status, means settlement have been performed on that.

For line items, go as Saurabh suggested.

Regards

Shishir

Former Member
0 Kudos

Hi Pabak,

Try combinations of AFVC (fetch AFVC-OBJNR) and COBRB tables to check whether the settlement has been carried out for the particular network.

Regards

Varun

former_member195427
Active Contributor
0 Kudos

Hi

Have a look in t-code CJIC and table COBRA, COBRB.

Regards

Saurabh

sanjeevc
Active Contributor
0 Kudos

Hi,

CJ8G use this transaction for know to settlement done for network and project, just create a variant for it and execute CJ8G transaction with variant input you will get desired result.

CN47n is the transaction for activity status know just filter here for SETC that means those activity have settlement done status.

CN42n is for WBS status here can also filter the same and identified in status of wbs.

Regards,

Sanjeev

Former Member
0 Kudos

Hi Pabak,

You can use Transaction code KOSRLIST_PR to see all the details of Settlement against any Project or Network.

Regards

Shashank Gaur