on 06-23-2014 9:54 AM
Hi All,
I faced a system error message"An invalid mode priority was specified for a mode" when I create a plan order in APO with PDS .
The PDS is only one activity/mode and the mode priority is blank.
After I maintained the mode priority, it worked.
Is that mean, even I don't have other mode, I should maintain the mode priority?
Thanks.
Hi Geoffrey.
I believe (not 100% sure) the mode priority should be 'A' by default, is this not happening? Do you have a badi implemented in ECC that could be clearing the mode priority?
Regards,
Tiago