Hi All,

I have a requirement where in I  have to add days which is GR processing time of product to a given date.

I found FM: /SAPAPO/MSDP_SNPHEU_DAYS_ADD.

But I am getting error:

Entries for time stream <Cal> have not yet been maintained.

any idea about the error or is there any other FM?

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member190993
Active Participant
0 Kudos

Hi Shraddha,

Its not clear if you want SNP heuristic planning to consider the GR processing time or writing a Zprogram to consider GR processing time.

If you want GR processing time to be considered in SNP planning, then please note as a standard functionality SNP heuristic considers the GR processing time maintained in the product master.

If writing a Zprogram and having issue with time stream field in the said FM, you may refer to time stream table /sapapo/tcalperi, wherein you can take the correct format for the time stream which you can use in this function module.

Hope this helps!

Regards,

Umesh

Former Member
0 Kudos

Hi,

Why don't u use the GR time field in product master.

Thanks, Nikhil