getting budget error for the exempted cost element also

Former Member
0 Kudos

I have exempted the cost element from budget check and re-construct the availability control.

For some transactions it allows me to make the transaction , but after some transaction it shows error again , than again i need to reconstruct the

availability control.

How can I make permanent solution for this.

Regards

Surya Baldwa

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member195427
Active Contributor
0 Kudos

Hi

If your issue is that you have to reconstruct AVAC and project info database many times then I would suggest you to go with automatic background jobs for the following programs:

PS_RPSCO_REBUILD : reconstruct project info database.

RBPFCPN1                 : reconstruct AVAC

You can take help of ABAPer or check the following document on it:

Regards

Saurabh

Former Member
0 Kudos

have you also reconstruct the Project info database? Run CJEN & CJBN in seq. And Check again.