Balance of WBS xxxxxxx is not zero

former_member223190
Participant
0 Kudos

Hi

My client when  trying to close the WBS , and message is displayed

"Balance of WBS xxxxxxx is not zero". He has already closed the WBS

as this was a warning. His question why has this message poped up.


CJI3 reports says that the balance of this WBS element is zero and no cost is associated with this WBS.

CJI5 reports says that there is some commitment cost arising form PR and PO. Is this cost responsible for the

message to be displayed. If yes what should be done so that this message should not displayed going forward.


If there any other reason's for this message to be displayed please let me know.



Thanks & Regards

Satish

Accepted Solutions (0)

Answers (4)

Answers (4)

former_member195427
Active Contributor
0 Kudos

Short close your PR- PO, Flag PO as 'Delivery Completed' followed by CJEN and CJBN run.

Regards

MTerence
Active Contributor
0 Kudos

Hi,

As per your information, there are some commitments available. Try clearing the commitments and close the WBS element.

This may be affecting since you have converted PR into PO.

We have a correction report to clear the negative commitments or incorrect commitments, search in OSS notes you will getting the same.

Also on the message front just check whether this is a warning message, if yes it will allow you to close.

Regards

Terence

Former Member
0 Kudos

Hi,

Have your performed settlement? Check your settlement profile using Tcode OKO7. Here is option "Can be settled" should be ticked if you want to close the project if bal is not 0.

After that execute settlement for WBS. And then try to close.

Regards

Shishir

Former Member
0 Kudos

Hi,

What ever you see in CJI3 might not be correct some times. There could be other reason to show up as such error message.

Please post the Error message number. Search forum with the message number so that you will get solution.

Thanks,

Sudhakar