Hi Team,
I have following requirement
Deliveries are created in SAP and processed to third-party WMS system for picking & PGI. Once WMS start picking these deliveries they want to restrict users from making any changes to these deliveries. Users can make changes before WMS starts the activity.
Picking & PGI are flown as inbound idocs to SAP.
What is the best way for achieving this requirement ?
Thanks
Rama
Hello Rama Krishna,
If it is not possible with SAP Standard settings, I will suggest to insert a enhancement in Delivery BAPI which will check for subsequent activity and not allow changes to the Delivery document.
Thanks,
Jignesh Mehta