Following the stepbystep document of Notes 1741109, we try to generate an Ibase component of a non-SAP system (called FLEXNET), on which we would like to use Administrative change document (SMAD) to track and follow the change in this system.
When creating the administrative change (ZMAD doc type), the Ibase component for this application is not proposed.
Here below my configuration:
From LMDB we created the product system/Product Version/Product instance and perform the necessary customizing point following the notes above.
With IB_GEN, the Ibase was generated successfully.
IB53
In SOLAR_PROJECT_ADMIN, the logical component have been assigned and Production system role set to the system FLEXNET
When creating the administrative change (ZMAD doc type), the component is not proposed from the match code: (only the SAP ibase ... which are working fine with Charm under Normal change)
and we got the error if we tried to record directly the ibase number in the field :
Error msg seems easy to understand ... but I do not solve it by myself!
Any idea ?
Many thanks!
I have opened a SAP message, and SAP reply that non-SAP application could NOT be used with Administrative Change SMAD.
They recommand to use General Change SMCG for that kind of Change ...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
Please select Change Relevant? check box on SOLAR_PROJECT_ADMIN txn the logical component screen. Right now I only see SBX marked relevant not the FLEXNET log component.
Let me know the result.
Regards,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
10 | |
9 | |
9 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.