Hello,
When i try to create a limit PO , under 'Follow-on documents' at header level , the flag for 'Confirmation-Related Invoice Verification ' is not set.
This leads to the status : Transfer Failed (E.Sys.)
As soon as i flag the check box 'Confirmation-Related Invoice Verification ' the PO is created correctly and transfered to the backend without error.
Could you please tell me how can i default this flag.
Regards,
Lina
Hi
Please refer to following OSS notes.
<b>Note 1022458 - Limit PO ends in Error Status: Document Contains No Items
Note 860026 PO response with new delivery date
Note 664522 Plan-driven service PO: Error during transfer to backend
Note 604420 Composite SAP note SRM 3.0 SP1 group
Note 518719 External requirement fulfillment fails with blanket PO
Note 518093 Confirmed extended purchase orders to appear in work list
Note 901840 list 'Error in transmission' shows 'approved', 'Transferred'
Note 983495 Error while transferring changed accounting data to backend
Note 906050 Resubmit failed service confirmations</b>
Regards
- Atul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
1. In the vendor master data under (transaction MK02) in R/3 go to the Purchasing Data for the particular vendor and maintain the flag Srv.-Based Inv. Ver.
2. If option 1 is too much implement BADI BBP_PO_INBOUND in R/3 and fill the service based invoice verification there.