Multi Mix resource - planned order dates not matching

Former Member
0 Kudos

Hi

We are facing planned orders dates mismatch in ECC and APO.

In ECC we have created work center as resource type ‘5’ – Multi mixed resource and its reflected in APO as Multi mixed.

We have 22 hors capacity available per day and number of individual capacities are maintained as 12

So total available capacity per day  = 246 hours

The capacity is showing up in APO correctly.

Also, in rate routing ‘required Splitting’ check box is ticked.

When planned order gets scheduled in ECC, system considers 264 available hours in a day and schedule planned order accordingly.

Problem is when plan order CIFed to APO, the days are not matching in ECC and APO.

Please suggest if we are missing any setting related t Multi Mix resource functionality.

Thanks in advance for your help!

Regards

Yogi

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Yogi

If you display one of these planned orders in ECC, on the header tab do you see only "basic dates" or do you see "production dates" too?

Chris


Former Member
0 Kudos

Hi Chris,

When we display planned orders in ECC, on the header tab we see both  "basic dates" and "production dates" .

Please suggest!

Thanks!

regards

Yogesh

Former Member
0 Kudos

Hi Yogesh

We had the same issue as you. Almost certainly, your planned orders are being subject to detailled scheduling after arrival in ECC. You need to configure a production scheduler with "no detailed scheduling" set in ECC for each plant. This should then be added to the material master data in field MARC-FEVOR. After this your planned orders will only display the basic dates and these will match those in APO.

Chris