Experts,
I am facing an issue for which your help is required.
One of my user is trying to change the investment program which gives the error -:
" WBS element PR/xxxxxx/xxxxxx is already budgeted or availabilty control is active"
Now my understanding is that in such a case the budget needs to be removed which will undo the user status BUDG and subsequently allow the user to make needfull changes.
I therefore went into IM52 and tried to delete the budgeted figure, upon saving I get an error "Overall budget is negative X - (value)"
Please guide me in the right direction to resolve this issue at the earliest.
PS --> This is a capex scheme .
rgds'
Mazal
Is that budget is already used? If yes, then can't be reversed/return. In this case you can't change the investment program also.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Mazal,
I think you need to return budget from WBS to Program/position id assigned to the WBS and make the budget figure 0 against WBS and reset the BUDG system status of WBS using t-code OPSX.
Regards
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Saurabh,
FYI - scheme status = CRTD
Are you referring to ME52 for returning the budget, I have tried this but apparently it throws the second error message as stated above.
Kindly state the tcodes wich I need to use.
Also please suggest, as this scheme's investment program states 'Approval Year = 2012', if I goto CJBW to deactivate Availability Control, change Investment Prg, goto CJBV to reenable Availabilty Control. Will this work??
Thanx in advance.