What is the dependency on SAP PI to upgrade ECC from EHP5 to EHP6

shankul_saxena
Explorer
0 Kudos

Hi Experts,

We are planning to upgrade from SAP PI 7.11 to SAP PI 7.4 and our ECC systems will also be upgraded from EHP5 to EHP 6.

I want to know that if there will be any upgrade required in Software Component Versions? We are using SCV as IS-UT 605, SAP ABA 7.00 and SAP BASIS 7.00,7.10,7.11.

Thanks,

Shankul

Accepted Solutions (0)

Answers (3)

Answers (3)

JuanDK78
Participant
0 Kudos

You will not have any issues with the SWCV for the Compoments you have listed.

However, in IDOC scenarios you will have to review the mapping because the IDOC_AAE adapter is very restrictive on using the right structures and the control record.

Some principles:

  • The parameter SEGMENT="1" must be used in all segments, if you have mapping that have disable it, the adapter will fail to read the mesage
  • DATE and TIME data types, if the IDOCs have been extender with field type Date or Time, then the format must be correct.
    • e.g. for a time field the format is HHMMSS, the value "1435" will fail,  it must be "143500"
  • The following fields are mandatory the in IDOC control record:
    • TABNAM
      DIRECT
      IDOCTY
      CIMTYP
      MESTYP
      SNDPOR
      SNDPRT
      SNDPRN
      RCVPOR
      RCVPRT
      RCVPRN
Former Member
0 Kudos

Hi,

You need to check the upgrade guide which will contain all the preparatory steps.

Regards,

Dimitri
Active Contributor
0 Kudos

Hi,

For EhP 5 and 6 , I think there are no dependencies.

When you want to upgrade your ECC system to EhP 7, please read OSS note 1737650.