Alternative Resource scheduling

Former Member
0 Kudos


Hi all,

We have requirement as below

1. Currently orders are scheduled on alternative resources A and B

2. We want to check orders causing overload on resource A and schedule it on resource B if capacity is available at same time on resource B if it is not available it should be de-allocated and kept at resource A. So we donot want order to look for capacity at backward or forward direction but only at same time if capacity is available on resource B it should shift it

3. Also it should schedule as many  orders as possible so rescheduling should get cancel as first scheduling error like it does in reschedule function

How this can be achived.

Regards,

Santosh

Accepted Solutions (1)

Accepted Solutions (1)

former_member182449
Participant
0 Kudos


Hi ,

Please try this Heuristic  SAP_MULT_SCH to switch modes and sources of supply according to defined time blocks

Regards

Rami

Answers (2)

Answers (2)

former_member182449
Participant
0 Kudos

Hi Santosh ,

Could you please check for me if this Heuristics can be used in online planning /SAPAPO/CDPSB0 ?

Or it can be used only in Detailed Scheduling Planning Board ?

I really appreciate your feedback

Regards

Rami

Former Member
0 Kudos

Hi,

Please check the Multi resource scheduling functionality.

http://help.sap.com/saphelp_SCM700_ehp02/helpdata/en/9f/032cda1aea4ce782b6def8c88fd2ab/content.htm?f...

Thansk