Hi,
I have configured DIP for capturing actual cost of working hours of enigineers working in the oil fields. ssytem capturing only cost in DMR followed by VF01 billing. but business wants to bill the customer through VF01 -revenue
Business scenario
i have a Servce contract -100000
In PS activity is confirmed for a worker (Engineer) for a month 200 hrs * 40 USD per hour = 8000 USD has to bill the customer
whenever the PS confirmation happens , sales team is creating DMR through DP91 , it is creating only 40 USD anf VF01 also 40 USD
I am unable to bill the customer as 8000 USD
Please guide me where i have missed out the configuration
Regards,
Pratheep
Hi Pradeep,
Go to transaction ODP2 , enter the DIP profile and execute. Send me the screen shot of 'Consistent check'.
This will help me to troubleshoot the issue.
Thanks
Regards
Srinivasan Desingh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
check your planning profile whether automatic planning check box is maintained like from sales order / from quotation.
net sales value is our revenue so after modification of this setting plan revenue would be update and after invoicing net sales value would be update then check in any revenue concern report and let me know....
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.