on 06-09-2014 12:57 PM
Hello Team,
Issue : I need propose a scenario where we need to recover the data in a table in case of any failure occurs (where point in time recovery is not possible) or there is mismatch in Target database (HANA) when compared to ECC source system.
The following are key constraints:
(in case of re-conciliation issue 1 hr downtime may be allowed as exception)
I have reviewed the documentation available and did not find any clear solution (steps) for recovery. How can we recover in the case of above scenario where replicating the tables again is not an option?
Please provide your viewpoint as this will be helpful in fast tracking the solution.
Regards,
Hemanth Aluri
Hi,
If you cannot recover to the last point in time, you can use the
replication logging feature that is available with the DMIS 2011 SP6.
Replication logging can be switched on for all tables of a
complete configurations via the checkbox ‘Activate Replication Logging’ at
the time when the configuration is created.
The SLT Application Operation Guide describes:
More details in chapter 6 of the Application Operations Guide: Application
Operations Guide
Best,
Tobias
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Tobias,
Thanks for your prompt response.I already have gone through this guide earlier.
The issue is the procedure highlighted in RED is not provided in more detail anywhere or at least I could not locate the same in SDN and SAP provided documentations. Could you please share me if there are any Links,documents in Detail how can I view this data and replicate it again from the SLT server system to the target system ?
Regards,
Hemanth Aluri