production order status for wm staging for production

Former Member
0 Kudos

Hi Friends,

What should be the status of production order for wm staging of raw for production.

In production order status Confirmed & delivered will I be able to do staging for the production order.

Thanks,

Kiran

Accepted Solutions (1)

Accepted Solutions (1)

former_member198492
Contributor
0 Kudos

Hi

Material staging should be allowed following the Release of the Production Order.

Then, as an example, you could have your first operation in the order (OP10) to Consume Materials. This will then backflush the materials in the PSA (Production Supply Area) that the staged materials were taken to. Ensure that the materials are set for Backflushing in the material master in MRP2.

If the OP10 is confirmed before materials have been staged then they will not appear in the LP12 staging report.

It's all about timing

Regards

Darren

Answers (1)

Answers (1)

MANIS
Active Contributor
0 Kudos

Hi Kiran

Best practice is It should be in Released status and not in TECO status

Former Member
0 Kudos

if  status Confirmed & delivered are we able to do staging.

MANIS
Active Contributor
0 Kudos

Hi,

Status Confirmed and Delivered comes after TECO hence you are not allowed to do staging against Confirmed and Delivered