on 06-06-2014 9:24 AM
Hi guru,
I need just some clarification about how works CN33
This is my scenario
Time T0: I have a WBS BOM with materials that need to be procured in advance. I run Cn33 and I assign these materials to activity A
Time T1: there is a change in my WBS BOM. I have added a HALB component with its BOM. When I run CN33, the system add this HALB to activity B but deleted the raw materials that I add in istant T0
Is it correct? I understand that CN33 works only on the changes to WBS BOM ...
Please, could you help me?
Thanks
Regards
Raffaele
Hi,
Could you please check activity A and let me know whether your newly added component HALB is reflecting on activity A or not.? Can you see all materials prior to addition of HALB on activity A.? Or the behavior on activity A is same as that of activity B.?
I am not sure but there are few points that you need to check.
1. Whether your newly added component is externally procured.? Just check MM03 settings for all previously added materials and newly added material HALB.?
2. Just check whether reference point for both the activities are same or not.?
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Amit, thanks for your answer
The reference points are different.
If I check activity after the second transfer, I don't see Raw materials.
Just for your benefit, when I set transfer rule in CN33, I fill the field reference point with *.
Maybe could be this the mistake? Could you please explain me how works CN33? maybe I don't understand
Thanks
Regards
Raffaele