on 06-05-2014 6:25 AM
Hi Friends,
I want to know logic for requested quantity calculation in LP10 as I see that there is stock available for the material but qty is not calcualted in requested quantity field.
Thanks,
Kiran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Requested quantity gets calculated based on how much left over stock you have in production supply area. Suppose in PSA available qty is 100pc and if you consumed only 70pc in the production order fow which you have staged it. SO left over stock will be will reduce the requested quantity by 30pc for next production order.
In your that may have happened, at first instance there might be some leftover stock was available, while next if might have consumed by someone
BR
Kamal
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.