on 06-04-2014 7:23 PM
Hi gurus!
I would like to do a subcontracting rework part in a project. I entered a purchasing
info record with a material master in a PS external processing operation. The system
returns the message CP561 “Enter info record without material”. What can I do
about it? There is a solution?
Best
Regards
Hello,
what i assuming based on your issue in project : Subcontracting process
Create subcon PR
Create Subcon PO
Create challan for sending material outside for subcontracting with specific movement type with A/C assignment Q
Once subcon process is done
Make GRN wrt subcon PO
Reconciliation challan
Error you are getting CP561 “Enter info record without material" although you said you have created info record in Me11 with material, so system giving error just anti,
if thing is not clear then let me know what your process for subcontracting?
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
In your case, you are intended to to procure service or an activity and not material. Since you are entered material as well as info record and hence giving an error.
Please note that external activities are not intended for procurement tangible material which does have material master data set up in the system.
Please do not enter a material and input only. Info record which has category 0 (normal) or 3 (subcontracting). Check with your MM consultant on this issue.
Thanks,
Sudhakar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.