Is there any user exit or BADI available which fetches information about milestones assigned to WBSe at save.
Thanks,
Akhil
Hi,
If you want to check changes in milestone assigned to a WBS. You can use tcode CN60 to track changes. I think, there is no need of BADI or exit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Shishir,
I understand CN60 can be used to track the changes. But the requirement is whenever there is a change in Basic fix date and Actual date of the milestone , an alert/email shall go to the cocern person and these condition shall be checked at save of the project. So, for this particular requirement i was looking for any BADI/exit which fetches milestone changes as soon as project is saved.
Thanks,
Akhil Rathi
Hi Akhil,
By using user exists you can validate data in the milestone fields (i.e basic fix date and actual date) . If user changes the date in the validated field, system cross checks with existing dates in mlst table and triggers a workflow event while saving project. discuss further with your technical consultant and check feasibility.
Regards,
Hi,
You can use CDPOS table to track changes from OLD value and New Value field.
Goto SE11/SE16->open Table CDPOS->Click on contents->give MLST on TABNAME field->execute
Now same thing above, you have to discuss with your abap/WF consultant that whenever changes occur in this Table as per above selection, mail notification should be trigger.
Discuss with them.
Regards
Shishir
User | Count |
---|---|
100 | |
11 | |
10 | |
6 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.