Hi

I have planned costs input in CJ40 against a WBS plan version "0" but when I run CJI4 no planned values are shown.

However if I run S_ALR_87013532 I can see the planned costs, why does CJI4 not show the costs?

thanks

Joe

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos


Hi,

CJI4 does not display plan cost eminated from CJ40.

Even to display the plan costs in CJI4 you need to have user status to be maintained "write plan costs' activated at WBS element level and costs should be planned using CJR2.

Just wanted to add here, S_ALR_87013532 is Hierarchy Cost Planning report - so you will see there.