The activity procedure date must be larger than the system date in VA42

0 Kudos

Please Help me...... I am trying to update the Contract End Date in VA42 but it is not updating and through an error message

''The activity procedure date must be larger than the system date''

please help me to solve the issue....

Thanks & Regards

Shakeel

Accepted Solutions (1)

Accepted Solutions (1)

andrea_brusarestelletti
Active Contributor
0 Kudos

Hello,

  in tab "Contract data" in the field "Action date" a date before or equal today's date is not allowed. So check your entries.

Best regards,

Andrea

Answers (7)

Answers (7)

0 Kudos

Hi all,

In VEDA table I found that Field 'Action Date rule' was not maintained.

So I have gone to Tcode: VA42 and in tab "Contract data" we have to maintained the field "Action date" and also Rule for that Contract .


-Shakeel

0 Kudos

Hi all,

Issue has been resolved  by myself.

Thanks to all......

Lakshmipathi
Active Contributor
0 Kudos

Shakeel Ahmed Mohammed

Please update how you solved so that it will be helpful to others who face similar issue.

G. Lakshmipathi

Former Member
0 Kudos

Hello Shakeel,

Is there any Contract Profile assigned in the sales Document For Contract.

Regards,

Rohit Dongre

phanikumar_v3
Active Contributor
0 Kudos

Normally all these contract data will be entered in Configuration--so please check what was the rule assigned for your contract profile???

IMG→SD→Sales→Sales Documents→Contracts→Contract data

Please update us...

Phanikumar

0 Kudos

Message no. V5031

former_member186385
Active Contributor
0 Kudos

Hi Ahmed,

If possible, could you update the error message number?

regards,

santosh

Lakshmipathi
Active Contributor
0 Kudos

Check the following note:-

  • Note 424082 - Message V5062 with contracts during creation with reference

G. Lakshmipathi