on 05-30-2014 4:43 PM
Hello Experts
I'm trying to copy planned delivery time of a material component into the activity duration and it doesn't work
Procedure:
the system responds as if I didn't do anything
can anyone help me please !!
Am I doing something wrong ?? can anyone tell me the procedure that works for him/her ??
Is there any configuration, business function activation or SAP Component installation to solve this?
Thanks for reading
Hi Ahmed,
I think it works only with internal activities.
Regards
Nicolas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear and everyone who looks into this.
Check this out, based on your reply I dug down and figured it out.
The Planned Delivery date for a material component is transferred <<Only from Material Master ""MRP2"">> into the duration field in internal tab for the activity. it doesn't copy the value from the material component.
The scheduling of the internal activity takes values from "Duration" in internal tab and transfers it to the "Duration" in Dates tab. the value in Duration in Dates tab is the only value effective for scheduling.
The scheduling of external activity inherits the dates duration from the Planned Delivery Time in EXTERNAL tab for the activity. and this is where we have a problem.
Solution:
Thank you for the Guidance.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ahmed,
Have a look in the following link::
Aligning Activity Duration with Material Lead Time - Material - SAP Library
https://help.sap.com/saphelp_46c/helpdata/en/a2/cd153805a49a5ce10000009b38f842/content.htm
Regards
Saurabh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for the reply Eng. Saurabh
After viewing all the three links I found that I've already done what's in link 1 & 2
as for the thread, it is not the problem I'm facing. I am facing a problem with copying the planned delivery time from material components to superior activity.
However, I tried setting the Start in the Past value to 999 as the thread said, maybe it's the answer, and nothing changed.
New Information
When I go to edit the Network in Special Maintenance CN22, go to the component overview, choose the component (Aligned to finish date) then go to "component" the "Duration dlv. time" option is Inactive.
Any Ideas !!!
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.